Create Your Badge Here's a compilation of questions from a UAPGA sponsored seminar. Enjoy!

 







Buy Rey a Beer :-) if you liked this Quiz, so I could post more!.

Related Posts

10 comments:

Anonymous,  June 1, 2010 at 8:47 AM  

for PP question , the ans should be 120,000.00 since we need 40% for all succeeding structures to be build

Anonymous,  October 24, 2010 at 4:47 AM  

60% for housing not 40 % repetitive ok?

Anonymous,  August 21, 2011 at 4:38 AM  

kindly check the spelling of bond. thanks

Anonymous,  August 26, 2011 at 7:04 PM  

Q.8) The approved form of security furnished by the Contractor as a guarantee of good faith on the part of the contractor to execute the work in accordance with terms of the Contract.
A. Guarantee Bond (your answer)
B. Surety Bond
C. Performance Bod (correct answer)
D. Payment Bond
.
Sir, pa verify nmn po ito sir.. thanks

Anonymous,  August 29, 2011 at 12:46 AM  

Performance bond is the correct answer, key word is EXECUTE the work in accordance with...
thanks

Anonymous,  September 24, 2011 at 11:08 AM  

Q.41) It is the third phase of English-Gothic Architecture where elaborated ornamental vaulting, and refinement of stonecutting techniques.

A. Perpendicular style (your answer)
B. Rayonnant style
C. Decorated style (correct answer)
D. Rococo style


Verify :)

Anonymous,  December 21, 2011 at 10:26 AM  

Yeah!It should be Perpendicular;

1.Early English (c. 1180–1275)
2.Decorated (c. 1275–1380)
3.Perpendicular (c. 1380–1520)

Anonymous,  January 12, 2012 at 11:04 AM  

It refers to contracts or arrangements involving the transfer of systematic knowledge for the manufacture of a product
A. Technology transfer (your answer)
B. Transfer of Record
C. Contract Documents
D. Technical Transfer (correct answer)

The correct answer po is Technology Transfer according to IRR RA 9266 Definition of Terms.

Anonymous,  January 12, 2012 at 11:32 AM  

Q.51) The _________ shall submit ________ copies of shop drawings for the architect’s approval

A. Engineer/ 5
B. Sub-contractor/4
C. Project representative/5
D. Contractor/2

Answer is D. Contractor/2 - but isn't it supposed to be 3 copies?

Anonymous,  January 22, 2013 at 11:53 AM  

it should be 2 if the project is small...but if the project is complex, or big project, it should be 3...

Post a Comment

Recent Comments

Followers

Blog Archive

About This Blog

*Architecture Education, Lecture Notes, Board Exam Review, Review Questions

*Modern Architecture, New Concepts, Design Innovations

*Sustainable Architecture, Green Architecture, Ecological Design, Veg.itecture, Green Technologies,Energy-Efficient Design,Climate-Responsive Design, LEED-Compliant Buildings, LEED Certification, Organic Architecture, Earth-sheltered Homes, Strawbale Housing, Bamboo Structures

*Student Thesis Projects, School Projects

  © Blogger templates The Professional Template by Ourblogtemplates.com 2008

Back to TOP