AMBF and PSO

    8

Here's a sample for determining the Allowable Maximum Building Footprint (AMBF) and the maximum allowable Percentage of Site Occupancy (PSO) from Rules 7 and 8 of the Revised IRR of the National Building Code of the Philippines (PD 1096).

8 comments:
Write comments
  1. Good day Sir. Is it possible to get a copy of your sample computations (slides) for Rules7&8?I am a student of yours in the refresher course and unfortunately was not able to copy most of the problems and computation from the lecture.Thanks!

    ReplyDelete
  2. From where did the value 24 (length of lot) came from?

    ReplyDelete
  3. the given area is 360Sqm.. 15 is the lot frontage
    15 multiplied by 24 is 360.... 24 is the length of the lot while 15 is the width

    ReplyDelete
  4. sir, where did you get the 4.50m setback @ one side of the lot... as you can see R-1 residential dwellings (single detached) indicated that the frontal is 4.50 and two sides including rear-side are all 2.00m setback & has given as per the nbc. how come you used 4.50m wide setback at one side., and i think your orientation is also wrong, based on your diagram. but i would like also to thank you for this problem solving. hope you'll add some more.

    ReplyDelete
  5. sir, just wanna ask, where did you get the 4.50 setback @ one side? as you can see in our nbc, R-1 residential dwellings (single detached) indicated that the frontal is 4.50m & 2 sides including rear side are all 2.00m setback only. please explain to us how did the setback on 1 side became 4.50. is it because the lot is at corner?? its not indicated at our nbc sir. but anyway i also like to thank you for this problem solving, hope you'll add some more.

    ReplyDelete
  6. sir, just wanna ask, where did you get the 4.50 setback @ one side? as you can see in our nbc, R-1 residential dwellings (single detached) indicated that the frontal is 4.50m & 2 sides including rear side are all 2.00m setback only. please explain to us how did the setback on 1 side became 4.50. is it because the lot is at corner?? its not indicated at our nbc sir. but anyway i also like to thank you for this problem solving, hope you'll add some more.

    ReplyDelete
  7. if its a corner lot, the sides fronting the two RROW would both have the larger setbacks. Its stated in Table for TOSL of the NBC.

    ReplyDelete
  8. sir, post a sample problem for GFA, TGFA, ISA and USA. please.

    ReplyDelete

Random Posts

  • Architecture History in the Philippines
    12.02.2009 - 1 Comments
    Here's an updated chronology of important events over the past 58 years relative to the Regulated Profession…
  • Online Review for JULY 2021 Master Plumber Board Exams
    24.02.2021 - 0 Comments
    In view of the global pandemic and quarantine rules the government has imposed, ATLAS-CDC…
  • Ten Most Unique Church
    29.01.2009 - 0 Comments
    Here is a list of some of the most unique churches in the world: Normal 0 …
  • Draft CPD Guidelines for Architects
    16.02.2017 - 0 Comments
    Here is the CPD FOR ARCHITECTS "DRAFT Operational Guidelines in the Implementation of RA 10912" as released…
  • The Unprofessional and Unethical “Justice”
    06.02.2012 - 6 Comments
    By Raison John J. Bassig THE COURT OF APPEALS (CA) on 05 January 2012 favored the petition of the Philippine…

ArkiReview

ATLAS_CPED ArkiReview

More Services

  • Send an Email

Blog Archive

© 2014 Architecture Overload. Designed by Bloggertheme9 | Distributed By Gooyaabi Templates
Powered by Blogger.