AMBF and PSO

    8

Here's a sample for determining the Allowable Maximum Building Footprint (AMBF) and the maximum allowable Percentage of Site Occupancy (PSO) from Rules 7 and 8 of the Revised IRR of the National Building Code of the Philippines (PD 1096).

8 comments:
Write comments
  1. Good day Sir. Is it possible to get a copy of your sample computations (slides) for Rules7&8?I am a student of yours in the refresher course and unfortunately was not able to copy most of the problems and computation from the lecture.Thanks!

    ReplyDelete
  2. From where did the value 24 (length of lot) came from?

    ReplyDelete
  3. the given area is 360Sqm.. 15 is the lot frontage
    15 multiplied by 24 is 360.... 24 is the length of the lot while 15 is the width

    ReplyDelete
  4. sir, where did you get the 4.50m setback @ one side of the lot... as you can see R-1 residential dwellings (single detached) indicated that the frontal is 4.50 and two sides including rear-side are all 2.00m setback & has given as per the nbc. how come you used 4.50m wide setback at one side., and i think your orientation is also wrong, based on your diagram. but i would like also to thank you for this problem solving. hope you'll add some more.

    ReplyDelete
  5. sir, just wanna ask, where did you get the 4.50 setback @ one side? as you can see in our nbc, R-1 residential dwellings (single detached) indicated that the frontal is 4.50m & 2 sides including rear side are all 2.00m setback only. please explain to us how did the setback on 1 side became 4.50. is it because the lot is at corner?? its not indicated at our nbc sir. but anyway i also like to thank you for this problem solving, hope you'll add some more.

    ReplyDelete
  6. sir, just wanna ask, where did you get the 4.50 setback @ one side? as you can see in our nbc, R-1 residential dwellings (single detached) indicated that the frontal is 4.50m & 2 sides including rear side are all 2.00m setback only. please explain to us how did the setback on 1 side became 4.50. is it because the lot is at corner?? its not indicated at our nbc sir. but anyway i also like to thank you for this problem solving, hope you'll add some more.

    ReplyDelete
  7. if its a corner lot, the sides fronting the two RROW would both have the larger setbacks. Its stated in Table for TOSL of the NBC.

    ReplyDelete
  8. sir, post a sample problem for GFA, TGFA, ISA and USA. please.

    ReplyDelete

Random Posts

  • Architecture Board Exam Review Questions
    09.07.2010 - 30 Comments
    Here is a sample quiz to gauge your preparations for the Day 1 afternoon session of the Architects board…
  • Is CPE mandatory or voluntary?
    18.03.2011 - 7 Comments
    “(RA 9266) SECTION 28. Continuing Professional Development (CPD). - To promote public interest and to…
  • RA 8749 Philippine Clean Air Act of 1999
    25.01.2010 - 0 Comments
    REPUBLIC ACT NO. 8749 PHILIPPINE CLEAN AIR ACT OF 1999 Chapter 1 General Provisions Article One Basic Air…
  • RA 9003 Ecological Solid Waste Management Act of 2000
    25.01.2010 - 0 Comments
    REPUBLIC ACT NO. 9003(ECOLOGICAL SOLID WASTE MANAGEMENT ACT OF 2000) AN ACT PROVIDING FOR AN ECOLOGICAL…
  • WHO SHOULD SIGN?
    19.06.2015 - 0 Comments
    Developments in recent years witness how the practice of architecture has been appropriated by many…

ArkiReview

ATLAS_CPED ArkiReview

More Services

  • Send an Email

Blog Archive

© 2014 Architecture Overload. Designed by Bloggertheme9 | Distributed By Gooyaabi Templates
Powered by Blogger.